projects
IN Progress!
Spearfish lunch loops
In August 2023, Rock Solid Trail Contracting joined us in Spearfish to develop our first comprehensive and ambitious concept plan for new trails and the expansion of existing ones on city-owned and city-leased land. We started with an initial vision of five zones and carefully refined it to four distinct zones that will encompass the entire project. In collaboration with the City of Spearfish, we’ve been diligently working to turn this vision into a reality.
Fundraising progress
Zones 2 & 3 in the process!
Zone 2: Skills Area Expansion
Zone 3: Gravity Skills Area
timeline & funding efforts
timeline & funding efforts
Timeline & Funding Efforts
Concept Report Completed: April 2023
Cost: $11,000 (Sponsored by SRAM)Detailed Design Completion: November 2024
Cost: $28,000 (Funded by private donors)Construction Phase Begins: Summer 2025
Funding Needed: Approximately $350,000 - $450,000 depending on the final design
Zone 1: Forebay
Location: City Lease, State-Owned Lands Without Existing Trail Development
Recommendations:
Construct machine-built gravity trails with a start hub
Develop an XC flow trail
Current Status: We are working on obtaining land approval from the City of Spearfish and South Dakota Game, Fish, and Parks.
Zone 4: Lookout Mountain
Location: City-Owned Land with Conservation Easement
Recommendations:
Build new beginner and intermediate trails to enhance the existing system
Reroute trails for improved sustainability
Create hike-only routes
Explore neighborhood connector opportunities
Current Status: The City of Spearfish is currently working on securing land use permissions for the Lookout Mountain Conservation Easement.